Anchored and over-optimistic: why quick and dirty estimates are almost always incorrect

with 7 comments

Some time ago, a sales manager barged into my office. “I’m sorry for the short notice,” she said, “but you’ll need to make some modifications to the consolidated sales report by tomorrow evening.”

I could see she was stressed and I wanted to help, but there was an obvious question that needed to be asked. “What do you need done? I’ll have to get some details before I can tell you if it can be done within the time,” I replied.

She pulled up a chair and proceeded to explain what was needed. Within a minute or two I knew there was no way I could get it finished by the next day. I told her so.

“Oh no…this is really important. How long will it take?”

I thought about it for a minute or so. “OK how about I try to get it to you by day after?”

“Tomorrow would be better, but I can wait till day after.” She didn’t look very happy about it though. “Thanks,” she said and rushed away, not giving me a chance to reconsider my off-the-cuff estimate.

After she left, I had a closer look at what needed to be done. Soon I realised it would take me at least twice as long if I wanted to do it right. As it was, I’d have to work late to get it done in the agreed time, and may even have to cut a corner or two ( or three) in the process.

So why was I so wide off the mark?

I had been railroaded into giving the manager an unrealistic estimate without even realising it. When the manager quoted her  timeline, my subconscious latched on to it as an initial value for my estimate.  Although I revised the initial estimate upwards, I was “pressured” – albeit unknowingly – into quoting an estimate that was biased towards the timeline she’d mentioned. I was a victim of what psychologists call anchoring bias – a human tendency to base judgements on a single piece of information or data, ignoring all other relevant factors. In arriving at my estimate, I had focused on one piece of data (her timeline) to the exclusion of all other potentially significant information (the complexity of the task, other things on my plate etc.).

Anchoring bias was first described by Amos Tversky and Daniel Kahnemann in their pioneering paper entitled, Judgement under Uncertainty: Heuristics and Biases. Tversky and Kahnemann found that people often make quick judgements based on initial (or anchor) values that are suggested to them. As the incident above illustrates, the anchor value (the manager’s timeline) may have nothing to do with the point in question (how long it would actually take me to do the work). To be sure, folks generally adjust the anchor values based on other information. These adjustments, however, are generally inadequate. The final estimates arrived at are incorrect  because they remain biased towards the initial value. As Tversky and Kahnemann state in their paper:

In many situations, people make estimates by starting from an initial value that is adjusted to yield the final answer. The initial value, or starting point, may be suggested by the formulation of the problem, or it may be the result of a partial computation. In either case, adjustments are typically insufficient. That is, different starting points yield different estimates, which are biased toward the initial values. We call this phenomenon anchoring.

Although the above quote may sound somewhat academic, be assured that anchoring is very real. It affects even day-to-day decisions that people make. For example, in this paper Neil Stewart presents evidence that credit card holders repay their debt more slowly when their statements suggest a minimum payment. In other words the minimum payment works as an anchor, causing the card holder to pay a smaller amount than they would have been prepared to (in the absence of an anchor).

Anchoring, however, is only part of the story.  Things get much worse for complex tasks because another bias comes into play. Tversky and Kahnemann found that subjects tended to be over optimistic when asked to make predictions regarding complex matters. Again, quoting from their paper:

Biases in the evaluation of compound events are particularly significant in the context of planning. The successful completion of an undertaking, such as the development of a new product, typically has a conjunctive character: for the undertaking to succeed, each of a series of events must occur. Even when each of these events is very likely, the overall probability of success can be quite low if the number of events is large. The general tendency to overestimate the probability of conjunctive events leads to unwarranted optimism in the evaluation of the likelihood that a plan will succeed or that a project will be completed on time.

Such over-optimism in the face of complex tasks is sometimes  referred to as the planning fallacy.1

Of course, as discussed by Kahnemann and Fredrick in this paper, biases such as anchoring and the planning fallacy can be avoided by a careful, reflective approach to estimation – as opposed to a “quick and dirty” or intuitive one. Basically, a reflective approach seeks to eliminate bias by reducing the effect of individual judgements. This is why project management texts advise us (among other things) to:

  • Base estimates on historical data for similar tasks. This is the basis of reference class forecasting which I have written about in an earlier post.
  • Draft independent experts to do the estimation.
  • Use multipoint estimates (best and worst case scenarios)

In big-bang approaches to project management, one has to make a conscious effort to eliminate bias because there are fewer chances to get it right. On the other hand, iterative / incremental methodologies have bias elimination built-in because one starts with initial estimates, which include inaccuracies due to bias, and subsequently refine these as one progresses. The estimates get better as one goes along because every refinement is based on an improved knowledge of the task.

Anchoring and the planning fallacy are examples cognitive biases – patterns of deviations of judgement that humans display in a variety of situations. Since the  pioneering work of Tversky and Kahnemann, these biases  have been widely studied by psychologists. It is important to note that these biases come into play whenever quick and dirty judgements are involved. They occur even when subjects are motivated to make accurate judgements. As Tversky and Kahnemann state towards the end of their paper:

These biases are not attributable to motivational effects such as wishful thinking or the distortion of judgments by payoffs and penalties. Indeed, several of the severe errors of judgment reported earlier (in the paper) occurred despite the fact that subjects were encouraged to be accurate and were rewarded for the correct answers.

The only way to avoid cognitive biases in estimating is to proceed with care and consideration. Yes, that’s a time consuming, effort-laden process, but that’s the price one pays for doing it right. To paraphrase Euclid, there is no royal road to estimation.

Footnotes:

1 The planning fallacy is related to optimism bias which I have discussed in my post on reference class forecasting.

Written by K

January 30, 2009 at 11:11 pm

Posted in Bias, Estimation, Project Management

Tagged with

7 Responses

Subscribe to comments with RSS.

  1. […] performance being 5)?” In earlier posts, I’ve written about the role of cognitive biases in project task estimation and project management research. The effect of these biases on performance metrics can be […]

    Like

  2. […] work of Kahnemann and Tversky – can be directly applied to project management (see my post on biases in project estimation, for instance).  In the papers, Shore looks at eight case studies of failed projects  and […]

    Like

  3. Hi Kailash,
    Great post. How does one react when asked to provide an order of magnitude estimate? Should it be whimsical? Will biases apply even when order of magnitude estimates are demanded?

    Like

    Prakash

    May 13, 2009 at 9:17 am

  4. Prakash,

    Thanks for your comments.

    In my experience, there are at least a couple of things to be considered when giving order of magnitude estimates.

    Firstly, it means different things to different people: to the estimator it may mean, “I can be off by a factor of 10” whereas to the requestor it may be, “The estimate should have an error of no more than 50%”. So the first issue is to clarify what is meant by the term.

    Secondly, on what basis does one make such an estimate? The only true guide is experience. However, one is typically asked for such estimates in situations where experience is lacking. In such cases it is very easy to be “conned” (via anchoring, say) into providing an estimate that’s off by several (hundred?) miles. The important point here is not to give off the cuff estimates, but to think things through or – better yet – consult others who have relevant experience. It’s all too easy to be pressured into giving numbers one may regret.

    Regards,

    Kailash.

    Like

    K

    May 13, 2009 at 6:40 pm

    • Thanks Kailash. The way you started this post (manager barges in and demands an estimate) is a typical scenario many of us should have experienced. Anchoring bias turns estimates into guesstimates. You have wonderfully correlated Agile and risk mitigation when it comes to biases. Looking forward to your next post

      Like

      Prakash

      May 15, 2009 at 9:06 am

  5. […] of thin air” by management serve as an anchor for subsequent estimation by the project team. See this post for more on anchoring in project situations. Anchoring is a meta-risk because the over-reliance on […]

    Like

  6. […] effort involved in a project task through a combination of anchoring and/or over-optimism  (see this post for a detailed discussion of these biases at work in a project situation). Further examples can be […]

    Like


Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.